[headline]CES have recently begun the commissioning phase of Eli Lilly’s latest Biotech Facility IE43.[/headline]

The CES commissioning package includes:

  1. 29 Air Handling Unit SystemsEli-Lilly-Logo
  2. 9 Biosafety Cabinet Systems
  3. 3 Dispensing Booth Systems
  4. 4 Cold Room Systems
  5. 1 degree and 4 degree Glycol Systems
  6. Low Temperature Hot Water System
  7. Vent Header System

 

CES will also undertake the balancing of all Utility and HVAC Systems in the facility.

CES involvement on all the above systems encompasses everything from design through to handover to site PQ including:

  1. Design Review
  2. Factory Acceptance Test review and execution
  3. Receipt Verification execution
  4. Protocol Generation (All Commissioning and Qualification Protocols)
  5. Site Walkdowns
  6. Punchlist Generation

 

The above project marks another exciting milestone for CES in terms of company growth & expansion and we look forward to delivering another successful C&Q project to such a valued client as Eli Lilly.

 

See below link for more details on the IE43 project

IDA News Article……

By |2018-11-13T23:25:38+00:00April 22nd, 2014|CESL News, Company News|0 Comments

About the Author: